Responsibilities of Contractor

Guam Code AnnotatedTitle 5 — Government Operations
View official PDF ↗

(a)The Contract shall require that the Contractor be responsible for all costs, expenses and fees of any kind or nature, associated with the design, civil improvements, on-site infrastructure, construction, permits and financing associated with the completion of an Education Facility. The Contractor shall also be responsible for the capital maintenance and upkeep of the schools during the Lease-Back term.

(b)The costs of the design, construction and financing for an Education Facility shall be paid in periodic installments over the term of the Lease-Back period, which shall be mutually determined by the Education Agency and the Contractor, but which will not exceed thirty

(30)years.

(c)The Lease and Lease-Back may provide that if sufficient funds are not appropriated or otherwise available for the payment of such installments, the Education Agency will have the obligation to vacate the Education Facility, and the Contractor shall have the right of use and occupancy of the Education Facility for the remainder of the term of the Lease, unless new mutually satisfactory terms are entered into. For this purpose, the Lease may provide that its term shall be extended for a period not to exceed the shorter of ten

(10)years beyond the original term of the Lease-Back or such period of time as is necessary to repay in full any financing arranged pursuant to Section 58108.

(d)The capital maintenance, repair and upkeep costs shall be paid on a periodic basis as incurred by the Contractor on terms to be agreed to in the Contract for each Education Facility. COL292017 CH. 58 THE EDUCATION FACILITIES CONSTRUCTION INITIATIVE ACT OF 2001

§ The story of this section

  1. Enacted by P.L. 26-61 § 2 — introduced as Bill 161-26 · introduced by Lawrence F. Kasperbauer
  2. Amended by P.L. 28-47 § 5 — introduced as Bill 101-28 · introduced by Lawrence F. Kasperbauer

Interpreted by the courts:

  • 2006 Guam 5In re Request of Governor Felix P. Camacho Relative to the Interpretation of Section 11 of the Organic Act of Guam and t (2006) · cited at ¶3

Reconstructed from the Guam Code Annotated. For the authoritative version, see the official PDF.