View official PDF ↗In the conducting of any hearing pertaining to the implementation of the provisions of the act authorizing the emergency procurement of generating equipment (P.L. 21-117) the Commission shall be exempt from the provisions of § 12117 of this Chapter. The Commission is requested to act upon any request of the Guam Power Authority (“GPA”) having to do with the implementation of such act expeditiously in order to enable GPA to timely accept such bids as it has received as may be approved by the Commission; provided, however, that the Commission’s authority under § 12105 of this Chapter to determine the need, prudence and timing of contracts and obligations contemplated by such act is recognized and confirmed.